New road project to ease traffic between Dubai and Sharjah to open in June
Now Reading
New road project to ease traffic between Dubai and Sharjah to open in June

New road project to ease traffic between Dubai and Sharjah to open in June

The project is slated to increase the traffic flow to about 12,000 vehicles per hour in both directions

Avatar

A new road project that is expected to ease the traffic movement between Dubai and Sharjah is almost complete and is set to be opened next month, the Dubai Roads and Transport Authority (RTA) has announced.

The Tripoli Street improvement project is now 90 per cent complete, the RTA said in a statement.

The 12-km street, which links Sheikh Mohammed bin Zayed Road and Emirates Road, acts as a parallel road to the recently re-opened Airport Street improvement project.

The project is expected to be opened by the end of June this year.

“The project will enhance the link between Dubai and Sharjah, ease traffic movement and streamline the access to Warqaa and Mirdif districts,” explained Mattar Al Tayer, director-general and chairman of the RTA.

“It will also improve the traffic safety at the intersections with Rabat and Nad Al Hamar Streets nearby of Bel Remaitha Club.”

The project is slated to increase the traffic flow to about 12,000 vehicles per hour in both directions (6,000 vehicles per hour per direction) and reduce the traffic volumes by 30 per cent. Upon completion, it will also act as a parallel to the Al Amardi–Al Khawaneej and the Al Awir – Ras Al Khor traffic corridors.

The project includes the widening of Tripoli St. over a 6.5km stretch from the intersection with Sheikh Mohammed bin Zayed Road (near Mirdif City Centre) up to Sheikh Zayed bin Hamdan Al Nahyan Street.

It also includes the construction of a new 5.3km long street of three lanes in each direction from the intersection of Tripoli-Sheikh Zayed bin Hamdan Al Nahyan Streets up to Emirates Road.

The Tripoli-Algeria Streets junction will be upgraded to a tunnel of three lanes in each direction while the existing intersection will be changed to a signalised junction.

“The completion of these works will cut the waiting time at the intersection from three minutes to less than a minute,” said Al Tayer.

The project also includes upgrading the existing roundabout at the intersection of Tripoli- Sheikh Zayed bin Hamdan Al Nahyan Streets into a flyover to ensure free movement of vehicles in all directions.

It also covers the construction of collector roads to serve the turn movements, two underpasses for camel crossings and widening the camel crossing No (3) at Emirates Road.

Works also include constructing a three-lane bridge to serve the traffic inbound from Tripoli St. to Emirates Road in the direction of Sharjah, widening Tripoli Road at several locations along with improvements at Bel Remaitha Club and two signalised junctions to replace existing roundabouts at Muhaisina.

The RTA will also build a three-lane bridge to serve the traffic from Tripoli St. to Emirates Road in the direction of Sharjah, and a surface intersection for the traffic inbound from Sharjah heading to Emirates Road.

“Work is progressing at a fast pace in the project. The contractor has completed the extension of Tripoli St. from the intersection with Sheikh Zayed bin Hamdan Al Nahyan St. up to Emirates Road and the bridge linking the extension of Tripoli St. with the Emirates Road in the direction of Sharjah,” said Al Tayer.

“Works were also completed in the flyover between Tripoli St. and Sheikh Zayed bin Hamdan Al Nahyan Street. Completion rate has reached 92 per cent in the bridge at the intersection of Tripoli-Nouakchott Streets, and 75 per cent in the tunnel at the intersection of Tripoli-Algeria Streets (Mirdif-Warqaa),” he said.

The RTA is currently carrying out a five-year internal roads plan (2019-2023) which covers the construction of internal roads in several residential districts across Dubai.

Read: Dubai’s RTA awards Dhs500m contract for Al Khawaneej roads project